Sewer Found, Risks Managed: DGC Ltd Awaits Engineering Sign-Off

Date: Week Ending 14 October 2024

The first sewer pipe has now been located, lying directly above the connection sewer. Engineers have been called to assess potential interference with nearby telecom chambers. In the meantime, further grout pours have stabilised the plant room floor beneath the hot water tank. CCTV security and overnight police checks remain in place due to the high-risk excavation area. DGC Ltd is awaiting an MU visit for precise sonde location, now that excavation is beneath most service lines.

Have a project in mind?

If you’re planning a project and want expert guidance from the ground up, we’d be happy to help. 

Get in touch with the DGC team to discuss your plans and find out how we can support you every step of the way.